Picture depicts secondary clarifier on the far left with primary clarifier to the right followed by the four cell aeration basin. Mill is to the right.

PROJECT: TMP / SULPHITE PULP AND PAPER MILL EFFLUENT TREATMENT PLANT
LOCATION: Chandler, Quebec
OWNER: Abitibi-Price
DESCRIPTION: The effluent treatment plant handles a flow of 28,000 m3/d and a BOD load of 25 t/d. Treatment consists of a spill basin, pH adjustment, primary clarifier, four cell activated sludge basin, nutrient addition, mechanical surface aerators, gravity belt sludge thickening and sludge screw press.
ROLE: Pre-design, process design, equipment selection, operator training and start-up assistance.